"Capital Smart City: Another master piece from the Capital Smart City launched one of its kind innovative & futuristic development - One Capital Residence." " "Nova City Islamabad has announced Nova City World - Overseas Block for its valuable customers. This state-of-the-art complex will offer luxurious modern amenities. " "Smart City has signed a MoU with Surbana Jorung. This will boast the position of Silicon Valley. " " Surbana Jorung will also design Cultural Village and some other miscellaneous projects" "RUDN Enclave: Development work in RUDN Enclave is on full swing. FWO also started construction of proposed Rawalpindi Ring Road." "Lahore Smart City’s new partnership with Galeria Designs, Raees Fahim, and Faisal Rasul. The future looks bright for Signature Villas!" "Dr Daniel been assigned the task of designing One Capital Residences would surely give birth to an aesthetic giant amidst the twin cities." "Alhamdolillah, with the grace of almighty Allah 2xHybird Double Decker Busses reached safely at Capital Smart City." "Capital Smart City has taken a pivotal step towards water filtration. This the filtration plant of capacity 4.5 Million Gallons per Day (MGD)."
October 15, 2021
CDA, FWO Officials Visit Low-Cost Housing Project Site In Alipur Farash
0 Comments

CDA, FWO Officials Visit Low-Cost Housing Project Site In Alipur Farash

Islamabad: The top brass of Capital Development Authority (CDA) and Frontier Works Organization (FWO) visited the construction site of the low-cost housing project underway in Alipur Farash, news sources reported.

The said low-cost housing project is a joint venture between the Naya Pakistan Housing & Development Authority (NPHDA) and CDA, which aims to build 2,400 apartments in the federal capital city. According to the plan, 400 of these units would be allocated to Katchi Abadi inhabitants, while the remaining would be offered to the general public.

As per the briefing, building work is now being carried out with 1,000 personnel, with the number expected to grow to 3,000 to 4,000 in the following months to enhance the project’s pace and completion of the project in stipulated time. Furthermore, the following updates were shared from the site:

  1. A total of 26 blocks have been excavated
  2. The raft has been built in two sections
  3. For 16 blocks, a steel cage for columns has been created
  4. Lean has been implemented in 21 blocks
  5. More than 60% of the site’s soil preparation for road development has been completed
  6. An on-site quality testing laboratory to save time and monitor building quality has been established